The Method Cabin – Construction Process


17
May 08

Week 6 – Factory Prefab Home Progress

Attached are some updated photos. The set is fast approaching and I see long work days next week but am excited to see this become reality after all of the work our team has put into it.

Method Homes was featured on Inhabitat’s prefab Friday.

Photos

These are the stacked roof components that be craned on after the five modules are set. We are calling this the "cold roof" since the insulation is in the ceiling of the modules. The "cold roof" serves to provide the home with overhanging eaves that protect the home and distinguish it architecturally, and also provides structural strength to allow the home to go in areas with hight snow loads such as Montana, the Methow Valley, and Whistler.

These are the stacked roof components that be craned on after the five modules are set. We are calling this the "cold roof" since the insulation is in the ceiling of the modules. The "cold roof" serves to provide the home with overhanging eaves that protect the home and distinguish it architecturally, and also provides structural strength to allow the home to go in areas with hight snow loads such as Montana, the Methow Valley, and Whistler.

Another picture of the roof components. Mark has action shots of them being stacked which he'll hopefully post soon. The actual stacking of the roof should make for an entry of its own.

Another picture of the roof components. Mark has action shots of them being stacked which he'll hopefully post soon. The actual stacking of the roof should make for an entry of its own.

This is Bedroom 3 in the back "bunkhouse" module and I'm quite please with how the tongue and groove paneling came out.

This is Bedroom 3 in the back "bunkhouse" module and I'm quite please with how the tongue and groove paneling came out.

Here is the bathroom where you can see the beginnings of the Toto dual flush toilet, Marmoleum and tile from the good folks at Statements Tile who are committed to sustainability http://www.statementstile.com/sustainability.aspx

Here is the bathroom where you can see the beginnings of the Toto dual flush toilet, Marmoleum and tile from the good folks at Statements Tile who are committed to sustainability

The beginnings of the radiant system.

The beginnings of the radiant system.

Here is a shot of the kitchen and visible is the vapor barrier that goes on top of the insulation before the tongue and groove ceiling.

Here is a shot of the kitchen and visible is the vapor barrier that goes on top of the insulation before the tongue and groove ceiling.

These are the tongue and groove boards that I have personally been pre-finishing. It has been a pet project of mine and has taken some time but its been fun putting some music on, zoning out and pre-finishing and I'm proud how they've come out.

These are the tongue and groove boards that I have personally been pre-finishing. It has been a pet project of mine and has taken some time but its been fun putting some music on, zoning out and pre-finishing and I'm proud how they've come out.


10
May 08

Week 6 – Coming down the homestretch

It has been a while since either of us has posted an update so here goes. Pictures will follow on Monday. Drywall and paint are complete. The tile and Marmoleum have gone on. The radiant heating system is being put together and next week we will install the tongue and groove ceiling, trim, and do finish electrical. Additionally, the roof components will be finished and stacked.

We also had KOMO 4 Seattle news to the production facility last week. The segment has aired several times and I think it was a good piece.

We are sending the home out the door on May 21 and setting it on the 22nd. This will be less than 7 weeks from the start. Mark and I are looking at each other in disbelief but as long a everything(cabinets) show up when it is supposed to the module will leave the factory 90% complete with cabinets, counter tops, and plumbing and electrical fixtures installed.

I am very pleased with the response we’ve had thus far, we have had good press coverage, expect some magazine profiles and have a number of parties interested in homes. It has been a group effort and all our master craftsmen, consultants and Scott and TomĀ  at Balance Associates have gone the extra mile to help us get to this point.

On a side note I have been thinking about all of the great vacation home spots where the Method Cabin should go. The list is long and I am reminded of all the beautiful locales out here.

I think Whistler would be a fantastic, close locale and some others include Bachelor, Hood, Montana, Idaho towns such as Sandpoint and Ketchum, and of course the Methow Valley and Leavenworth areas of Washington. The San Juan Islands also make good sense because the time and cost of construction out there. Basically anywhere a vacation home can go in the Northwest and beyond. I am thinking about doing a promotional tour of these areas this summer. The beauty of the Method Cabin is the siding and exterior appearance can be modified for each of these locations in order to be in harmony with different natural surroundings.

I will post in greater detail about our no VOC Yolo Colorhouse paint, radiant system, reclaimed trim and Marmoleum shortly.


28
Apr 08

Week 4 – Foundation In Forest/Slag

The foundation is sitting in the woods, awaiting a home. I can’t wait to see it. The warehouse has sheet rock hung and by the end of the week a level 5 smooth wall. The home is scheduled to leave May 21st. See you soon!

Brian chiming in here. This is probably a good time to go over the concrete slag that made up 50% of our concrete. We will be earning LEED points from slag and based on all the benefits of using it with no drawbacks I think it should be used in all projects. From the slag cement association slagcement.org

“Slag cement is a byproduct of an iron blast furnace, part of an integrated steel mill. When molten slag is separated from iron in a blast furnace, it can be rapidly quenched with water (“granulated”), dried and ground to a fine powder. At this point it becomes slag cement (or ground granulated blast furnace slag)

Slag cement is one of the most sustainable construction materials available because it:


24
Apr 08

Week 3 – In Factory – Insulation

Yesterday the foam crew from Burnham Insulation was up to the facility applying 2 inches of spray polyurethane foam. This is going to give the home a tight building envelope allowing no air penetrations and thus increasing energy efficiency.

Coupled with the blown in cellulose that was applied today the home is going to achieve a R value of 25.

I am amazed that we are only 3 weeks into the building process and will be hanging sheet rock tomorrow. We have completed rough electrical, rough plumbing, insulation and all framing and the foundation was just poured this past Monday. On top of that everything is bone dry inside the home and we’re on schedule. Actually witnessing construction take place has made me even more a believer in factory built homes than I was already and that is saying a lot. We are on schedule to build the home in 7 weeks which is incredible to me since I am now finishing a site built home that was started in August.

In business news I’ve been working hard forming strategic partnerships with product suppliers and am happy that we are working with Yolo Colorhouse for paint, KlipTech EcoTop for counters, TimberPro Coatings for low VOC exterior stains and several other companies that I’ll list later.

We also sent out our first press release and hopefully there will be some new people reading this after we receive some coverage. Launching a startup is equally exhilarating and exhausting but I love and believe in what we’re doing so it is gratifying as well.


16
Apr 08

Week 2 – Framing Signed Off, Foundation Poured

Hello everyone. Today we finished framing as we were signed off by Labor and Industries on Sheer and Framing. Rough electrical started today. Tomorrow we will be setting windows as well as rough plumbing. And on site, progress is being made as the foundation has been poured.


10
Apr 08

Week 2 – Day 8 – Factory Prefabrication – Framing

The Method Cabin is coming to life. All ext. walls are up and ready for shear inspection. Tomorrow, our mechanical sub will be on site to install the Pex tubing in our Warmboard. When he is finished we can move on to the interior walls. Looks like a few more days of framing on the interior walls and warm roof…all in all I think we are ahead of schedule.


10
Apr 08

Week 2 – Bamboo Cabinets & Architect Meeting

Today we finalized a partnership with Seattle company Bamboo Hardwood to be Method Home’s preferred supplier of cabinets and flooring. They are going to build us very cool solid core bamboo cabinets, vanities and armoirs that I’m quite excited about having in the Method Cabin.


8
Apr 08

Week 2 – Factory Prefabrication – Walls & Insulation

The construction of the walls bring concept into reality

The construction of the walls bring concept into reality

Foam insulation is applied

Foam insulation is applied

Bamboo flooring and walls

Bamboo flooring and walls

The modular units are almost ready

The modular units are almost ready


4
Apr 08

Week 1 – Factory Prefabrication – Framing and Floors

Framing Begins

Framing Begins

1st day and already lots of progress

1st day and already lots of progress

FSC certified lumber

FSC certified lumber

Warmboard is placed

Warmboard is placed


2
Apr 08

Week 1 – On Site Construction – Home Site Before Construction Begins